Brecon Beacons National Park Authority - Progress in delivering Statutory Recommendations: report cover showing Audit Wales logo
Brecon Beacons National Park Authority – Progress in delivering Statutory Recommendations
08 March 2022

The Auditor General for Wales published his report on Delivery of the Change Programme at Brecon Beacons National Park Authority in February 2021. Overall, we concluded that weaknesses in leadership and governance were highlighted by poor management and delivery of the major change programme initiated by the Authority in October 2019.

Delivering the Auditor General’s statutory recommendations has been hindered by continuing governance problems and a lack of capacity and the Authority should now seek the assistance of Welsh Ministers to address these problems.